At the time of booking |
10% of total consideration + GST |
At the time of agreement |
10% of total consideration + GST |
On completion of piling of respective towers |
10% of total consideration + GST |
On casting of 1st floor slab of respective tower |
10% of total consideration + GST |
On casting of 4th floor slab of respective tower |
5% of total consideration + GST |
On casting of 6th floor slab of respective tower |
5% of total consideration + GST |
On casting of 8th floor slab of respective tower |
5% of total consideration + GST |
On casting of 10th floor slab of respective tower |
5% of total consideration + GST |
On casting of 12th floor slab of respective tower |
5% of total consideration + GST |
On casting of 14th floor slab of respective tower |
5% of total consideration + GST |
On casting of 16th floor slab of respective tower |
5% of total consideration + GST |
On casting of roof slab of respective tower |
5% of total consideration + GST |
On completion of brick work of respective tower |
5% of total consideration + GST |
On completion of external plaster of respective tower |
5% of total consideration + GST |
On or before the date of possession |
10% of total consideration + GST + additional charges & deposits |